Case Studies
“GreenLite is proactive, not reactive. And that proactivity is what helps bring timelines down and get to the end result of receiving a building permit so much faster than anybody else.”
Ashley Shoults
Senior Director of Design
VEG ER for Pets
All Case Studies
-
How GreenLite Cut Florida Restaurant Permit Timelines by 30 to 45 Days with Private Plan Review
- 8 business days Fastest permit, submission to issuance
- 45 Days cut from typical permit timeline
- $5k of revenue at stake for every day a location isn’t open
-
How GreenLite standardized multi-state retail permitting for one of the country’s largest footwear companies.
- 14 average business days from submittal to AHJ approval
- 0.5 average AHJ resubmission cycles
- 4 permits issued across different states
-
How a Leading Fast-Casual Restaurant Brand Built a Scalable Permitting Operation Across 7 States with GreenLite
- 10 business days from application submission to plan approval, first permit, first try
- 19 projects managed across 15+ unique jurisdictions in 7 states
- 84% of projects with zero resubmissions
-
How a Leading National Retailer Cut Permit Timelines by Up to 120 Business Days
- 24 construction permits managed across Georgia, Florida, Tennessee, and Texas
- 61+ business days saved on the fastest project
- 0 resubmittals on first-submission approvals
-
How a Leading National Bank Secures Permits in Less Than 3 Weeks Across the U.S.
- +45 locations managed across CA, FL,TX, NY, & NJ
- 13 business days fastest permit, from submission to issuance
- 1.0 average AHJ revision cycles per project
-
How GreenLite became the permitting partner behind one of the fastest-growing emergency veterinary clinics in the country.
- 20+ hospitals opened with GreenLite
- 105 average days saved compared to AHJ averages
- 0.9 average resubmissions
- 14 states served
-
The New Path to Permits in Florida
- Fastest Permit Issued: 8 days
- Average Days Submission to Approval: 40 days
- Projects across 129 jurisdictions
- Allows licensed private providers to perform plan review
-
The New Path to Permits in California
- 800 Saved Days
- 28 Business Days, submission to permit
- 50+ projects managed
-
The New Path to Permits in Texas
- 10 Business Days Faster Permit
- 155 Days Saved
- <1 resubmission
-
The New Path to Permit in Tennessee
- Fastest Permit Issued: 4 days
- Average Days Submission to Approval: 25 days
- Allows licensed private providers to perform plan review
-
Dine Brands Global | National
- Permit Type: Mostly franchise, with growing corporate ownership
- Jurisdiction: 70+ Projects assessed across 60+ jurisdictions
- Approval Speed: 15 business days
- Revision Cycles: 0 Stop Work Orders across GreenLite-managed jobs
- Impact: 45+ Active Projects managed with full permit coverage
-
Driven Brands / Take 5
- Permit Type: Automotive Service Centers (Multi-Site)
- Jurisdiction: Nationwide
- Approval Speed: 24 business days on average
- Revision Cycles: <1 revision cycle per project
- Impact: 5x ROI on project cost
-
Chipotle | Royal Palm Beach
- Permit Type: QSR Ground-up Construction
- Jurisdiction: Village of Royal Palm Beach
- Approval Speed: 3 weeks (vs. 16 weeks projected)
- Revision Cycles: 0 municipal revision cycles
- Impact: $750K+ in potential revenue/cost savings