QSR Development
- 1-2 weeksSavings per Project on Commercial Building Permit Timelines
- $345+Meaningful dollars saved in revenue recapture, city fee reduction, and soft costs

Share:
Another Win for Faster Permitting
A Top 10 QSR brand cut their permitting timeline in half in Brandon, FL — from 20 planned weeks to 10! By partnering with @GreenLite and leveraging our Private Plan Review service concurrently with civil review, we went from submission to permit issuance at record speed.
📍 Jurisdiction: Brandon, FL – Hillsborough County
⏳ Projected Timeline: 20 weeks
⚡ Actual Timeline: 10 weeks (48 business days!)
💰 Estimated ROI: $1.6M+ in accelerated revenue capture
When time was critical, our ability to conduct concurrent reviews kept the project moving seamlessly. The result? A permit issued in half the time — even faster than an expeditor working on a similar site.
If you’re looking to simplify your permitting process and accelerate timelines, let’s connect!